Texas Lien Notice Deadline Calculator
In Texas, subcontractors and suppliers must send a notice of claim to the owner and the original contractor for every month of unpaid work – by the 15th day of the 3rd month after that month (2nd month on residential projects). The lien affidavit is due by the 15th day of the 4th month after the month you last worked (3rd month on residential). Tex. Prop. Code §§ 53.052, 53.056.
- Free, no sign-up
- Statute behind every date
- Text reminders
- Notice mailed certified: $29
- Ver en español →
Your deadlines
Texas deadlines by role and project type
| Step | Who | Deadline | Source |
|---|---|---|---|
| Notice of claim for unpaid work | Subcontractor, SupplierCommercial / other | 15th day of the 3rd month after the month of unpaid work | Tex. Prop. Code § 53.056(a-1)(1) |
| Notice of claim for unpaid work | Subcontractor, SupplierResidential (house, condo, up to 4 units) | 15th day of the 2nd month after the month of unpaid work | Tex. Prop. Code § 53.056(a-1)(2) |
| Notice of claim for unpaid retainage | Subcontractor, Supplier | 30 days after last furnishing | Tex. Prop. Code § 53.057(a-1) |
| File lien affidavit with the county clerk | Subcontractor, SupplierCommercial / other | 15th day of the 4th month after last furnishing | Tex. Prop. Code § 53.052(b) |
| File lien affidavit with the county clerk | Subcontractor, SupplierResidential (house, condo, up to 4 units) | 15th day of the 3rd month after last furnishing | Tex. Prop. Code § 53.052(c) |
| File lien affidavit with the county clerk | Prime contractorCommercial / other | 15th day of the 4th month after completion | Tex. Prop. Code § 53.052(a)(1) |
| File lien affidavit with the county clerk | Prime contractorResidential (house, condo, up to 4 units) | 15th day of the 3rd month after completion | Tex. Prop. Code § 53.052(a)(2) |
| Send a copy of the filed affidavit | Prime contractor, Subcontractor, Supplier | 5 days after recording the lien | Tex. Prop. Code § 53.055 |
| Last day to sue to foreclose the lien | Prime contractor, Subcontractor, Supplier | 1 year after the last day to file the lien | Tex. Prop. Code § 53.158(a) |
Worked examples
Electrical sub on an office build-out, October 2025 unpaid
Send notice
Notice of claim for unpaid work – October 2025
Act by
Thu, Jan 15, 2026
Last day by law
Thu, Jan 15, 2026
To: Property owner, General contractor
The 15th day of the third month after October 2025 = Thu, Jan 15, 2026.
Lumber supplier to a home builder, last delivery Nov 14, 2025
File lien
File lien affidavit with the county clerk
Act by
Fri, Feb 13, 2026
Last day by law
Sun, Feb 15, 2026extended by law to Tue, Feb 17, 2026
The 15th day of the third month after November 2025 (month of your last day of work or delivery) = Sun, Feb 15, 2026. Sun, Feb 15, 2026 is a Sunday; by law (Tex. Prop. Code § 53.003(e)) the period extends to Tue, Feb 17, 2026. Don't rely on the extension. We remind you to act by the last business day before: Fri, Feb 13, 2026.
Common mistakes
- Sending one notice for the whole job. Texas needs a notice for every month in which you worked and were not paid.
- Counting from the invoice date. The clock runs from the month the labor or materials were provided.
- Sending the notice only to the general contractor. It must go to the owner and the original contractor.
- Using pre-2022 rules. Since H.B. 2237 (Jan 1, 2022) there is no separate 2nd-month notice to the GC on commercial jobs.
- Waiting for the weekend extension. The law extends a deadline that falls on a weekend or holiday – but certified mail sent a day late is still late if your count is off.
The statutory form
LienBuddy fills in the form with your job data and copies the statutory wording word for word. View a blank sample (PDF)
Frequently asked questions
Does a supplier need to send monthly notices too?
Yes. Every claimant other than the original contractor – subcontractors at any tier and material suppliers – sends the notice of claim under § 53.056.
How must the notice be sent?
In person, by certified mail, or by another traceable delivery service that confirms receipt (§ 53.003). Mailing by certified mail counts on the day you deposit it.
What if I already got paid for some months?
Paid months need no notice. In the calculator, tap the months you were paid for. In your account we ask you every month.
When must I file the lien affidavit?
Subcontractors and suppliers: by the 15th day of the 4th month after the month they last provided labor or materials (3rd month on residential projects). Original contractors: counted from the month their work was completed, terminated or abandoned.
How long do I have to sue?
One year after the last day you could have filed the lien affidavit (§ 53.158), unless extended by a recorded written agreement with the owner.
Track this job & get SMS reminders
Free for up to 3 jobs. Email reminders 14, 7, 3 and 1 day before every deadline.
Start freeAlso see: Texas lien waiver forms · What is a mechanics lien?