Florida Mechanics Lien Deadline
In Florida, the claim of lien must be recorded within 90 days after your final furnishing of labor, services or materials, and served on the owner within 15 days after recording. You then have one year to sue – or only 60 days if the owner serves a notice of contest. Fla. Stat. §§ 713.08, 713.22.
- Free, no sign-up
- Statute behind every date
- Text reminders
- Notice mailed certified: $29
- Ver en español →
Your deadlines
Florida deadlines by role and project type
| Step | Who | Deadline | Source |
|---|---|---|---|
| Record Claim of Lien | Prime contractor, Subcontractor, Supplier | 90 days after last furnishing | Fla. Stat. § 713.08(5) |
| Serve the recorded Claim of Lien on the owner | Prime contractor, Subcontractor, Supplier | 15 days after recording the lien | Fla. Stat. § 713.08(4)(c) |
| Last day to sue to enforce the lien | Prime contractor, Subcontractor, Supplier | Earlier of: 1 year after recording the lien; 60 days after a notice of contest | Fla. Stat. § 713.22(1), (2) |
Worked examples
Roofer (sub), last day Dec 19, 2025
File lien
Record Claim of Lien
Act by
Thu, Mar 19, 2026
Last day by law
Thu, Mar 19, 2026
90 days after your last day of work or delivery (Fri, Dec 19, 2025) = Thu, Mar 19, 2026.
Common mistakes
- No Notice to Owner. Without a timely NTO the lien is not enforceable for anyone not in privity with the owner.
- Counting from the last invoice. The 90 days run from your final furnishing – punch-list or warranty work usually does not restart it.
- Not serving the recorded lien within 15 days.
Frequently asked questions
Who can file a mechanics lien in Florida?
Contractors, subcontractors and material suppliers who improved the property and were not paid – if they gave the required notices on time.
Does LienBuddy file the lien for me?
Not yet. We track the deadline and remind you early. For the lien itself we recommend a construction attorney or a lien filing service.
What if I don't know the completion date?
The calculator then assumes the earliest possible date and says so. Update the job when you know more.
Are weekends and holidays counted?
Yes – Chapter 713 counts calendar days and has no general weekend extension. We remind you to act by the last business day.
Is this legal advice?
No. LienBuddy is software that calculates deadlines from the dates you enter and shows the statute. Talk to an attorney if dates are uncertain or a lot of money is at stake.
Track this job & get SMS reminders
Free for up to 3 jobs. Email reminders 14, 7, 3 and 1 day before every deadline.
Start freeAlso see: Florida lien waiver forms · What is a mechanics lien?