California Preliminary Notice – 20-Day Deadline Calculator
In California, subcontractors and suppliers must give a preliminary notice to the owner, the direct contractor and the construction lender within 20 days after they first furnish work. A late notice still helps, but only covers work done in the 20 days before you serve it and afterwards. Cal. Civ. Code §§ 8200, 8204.
- Free, no sign-up
- Statute behind every date
- Text reminders
- Notice mailed certified: $29
- Ver en español →
Your deadlines
California deadlines by role and project type
| Step | Who | Deadline | Source |
|---|---|---|---|
| Send Preliminary Notice (20-day notice) | Subcontractor, Supplier | 20 days after first furnishing | Cal. Civ. Code §§ 8200, 8204(a) |
| Record Mechanics Lien | Subcontractor, Supplier | Earlier of: 90 days after completion; 30 days after a recorded notice of completion | Cal. Civ. Code § 8414 |
| Record Mechanics Lien | Prime contractor | Earlier of: 90 days after completion; 60 days after a recorded notice of completion | Cal. Civ. Code § 8412 |
| Last day to sue to enforce the lien | Prime contractor, Subcontractor, Supplier | 90 days after recording the lien | Cal. Civ. Code § 8460(a) |
Worked examples
Framing sub, first day Dec 22, 2025
Send notice
Send Preliminary Notice (20-day notice)
Act by
Fri, Jan 9, 2026
Last day by law
Sun, Jan 11, 2026extended by law to Mon, Jan 12, 2026
To: Property owner, General contractor, Construction lender
20 days after your first day of work or delivery (Mon, Dec 22, 2025) = Sun, Jan 11, 2026. Sun, Jan 11, 2026 is a Sunday; by law (Cal. Code Civ. Proc. §§ 12a, 135) the period extends to Mon, Jan 12, 2026. Don't rely on the extension. We remind you to act by the last business day before: Fri, Jan 9, 2026.
Equipment rental, first delivery Dec 12, 2025
Send notice
Send Preliminary Notice (20-day notice)
Act by
Wed, Dec 31, 2025
Last day by law
Thu, Jan 1, 2026extended by law to Fri, Jan 2, 2026
To: Property owner, General contractor, Construction lender
20 days after your first day of work or delivery (Fri, Dec 12, 2025) = Thu, Jan 1, 2026. Thu, Jan 1, 2026 is a holiday (New Year's Day); by law (Cal. Code Civ. Proc. §§ 12a, 135) the period extends to Fri, Jan 2, 2026. Don't rely on the extension. We remind you to act by the last business day before: Wed, Dec 31, 2025.
Common mistakes
- Skipping the lender. If there is a construction lender, it must get the notice too.
- Waiting until payment is late. Send the preliminary notice on every job within 20 days.
- Forgetting the estimate. The notice must include an estimate of the total price of your work.
- Ignoring a Notice of Completion. If the owner records one, your lien deadline drops to 30 days after recording.
- No proof of service. Keep the certified mail receipt and tracking – we store it with the job.
The statutory form
LienBuddy fills in the form with your job data and copies the statutory wording word for word. View a blank sample (PDF)
Frequently asked questions
Do general contractors send a preliminary notice?
A contractor with a direct contract with the owner only gives it to the construction lender, if there is one (Civ. Code § 8200(e)(2)). Laborers don't send one.
What if I missed the 20 days?
Send it now. You can still record a lien for work provided within 20 days before the notice and after it (§ 8204).
When is the mechanics lien due?
Subcontractors and suppliers: the earlier of 90 days after completion or 30 days after a recorded notice of completion or cessation. Direct contractors: 90 days or 60 days.
Do weekends and holidays extend the deadline?
Yes, under Code of Civil Procedure § 12a the period extends to the next business day. We still remind you to act before.
How long after recording do I have to sue?
90 days after recording the claim of lien (§ 8460), otherwise the lien expires.