Florida Notice to Owner – Deadline Calculator & Form
In Florida, subcontractors and suppliers without a direct contract with the owner must serve a Notice to Owner before they start or within 45 days after they first furnish labor or materials – and in any case before the owner's final payment. A missing or late Notice to Owner is a complete defense against your lien. Fla. Stat. § 713.06(2).
- Free, no sign-up
- Statute behind every date
- Text reminders
- Notice mailed certified: $29
- Ver en español →
Your deadlines
Florida deadlines by role and project type
| Step | Who | Deadline | Source |
|---|---|---|---|
| Serve Notice to Owner | Subcontractor, Supplier | Earlier of: 45 days after first furnishing; before the owner's final payment | Fla. Stat. § 713.06(2)(a) |
| Record Claim of Lien | Prime contractor, Subcontractor, Supplier | 90 days after last furnishing | Fla. Stat. § 713.08(5) |
| Serve the recorded Claim of Lien on the owner | Prime contractor, Subcontractor, Supplier | 15 days after recording the lien | Fla. Stat. § 713.08(4)(c) |
| Last day to sue to enforce the lien | Prime contractor, Subcontractor, Supplier | Earlier of: 1 year after recording the lien; 60 days after a notice of contest | Fla. Stat. § 713.22(1), (2) |
Worked examples
Drywall sub, first day on site Nov 20, 2025
Send notice
Serve Notice to Owner
Act by
Fri, Jan 2, 2026
Last day by law
Sun, Jan 4, 2026
To: Property owner, General contractor
45 days after your first day of work or delivery (Thu, Nov 20, 2025) = Sun, Jan 4, 2026. We remind you to act by the last business day before: Fri, Jan 2, 2026.
Concrete supplier, first delivery Dec 1, 2025, owner pays in full Jan 10, 2026
Send notice
Serve Notice to Owner
Act by
Fri, Jan 9, 2026
Last day by law
Fri, Jan 9, 2026
To: Property owner, General contractor
Earlier of: 45 days after your first day of work or delivery (Mon, Dec 1, 2025) = Thu, Jan 15, 2026; the day before the owner's final payment (Sat, Jan 10, 2026) = Fri, Jan 9, 2026. The earlier date counts.
Common mistakes
- Counting 45 days from the contract date. The clock starts on the first day you furnish labor, services or materials to the site.
- Waiting until you are not paid. Serve the Notice to Owner on every job – it costs little and keeps your lien rights.
- Wrong owner. Use the owner from the Notice of Commencement or the property appraiser, not the customer's word.
- Forgetting the contractor. Sub-subcontractors and suppliers to subcontractors must also serve a copy on the contractor.
- Changing the statutory wording. Use the form in § 713.06(2)(c) – our PDF copies it word for word.
The statutory form
LienBuddy fills in the form with your job data and copies the statutory wording word for word. View a blank sample (PDF)
Frequently asked questions
Who does not need a Notice to Owner?
Contractors with a direct contract with the owner, and laborers. Everyone else who wants lien rights serves it.
How is the Notice to Owner served?
Under Fla. Stat. § 713.18 – in practice by certified mail with return receipt to the owner's address from the Notice of Commencement. LienBuddy prints and mails it for you and stores the proof.
What if day 45 is a weekend?
Chapter 713 has no weekend extension rule for the Notice to Owner. We remind you to act by the last business day before.
When is the claim of lien due?
Within 90 days after your final furnishing (§ 713.08(5)), and it must be served on the owner within 15 days after recording.
Can I send the Notice to Owner in Spanish?
The statute prescribes English wording. Our app explains every step in Spanish, but the notice itself is printed in the statutory English text.